Critical Path
7 practice questionsProject ManagementStep-by-step solutions
Try a few
1
Tasks that lie on the critical path have a float (slack) of:
A.Zero
B.One week
C.Unlimited
D.Equal to the project length
2
The amount of time a non-critical task can be delayed without delaying the overall project is its:
A.Float (slack)
B.Duration
C.Lag
D.Baseline
3
The critical path of a project is the:
A.Cheapest sequence of tasks
B.Longest sequence of dependent tasks, determining the minimum project duration
C.Set of optional tasks
D.Path with the most resources